Nurek HPP is a hydroelectric power plant near the town of Nurek in Tajikistan on the Vakhsh River. Annual electrical energy generation: 11.2 billion kWh, installed capacity 3,015 MW

Nurekskaya HPP
date

started at 2004

finished till present days

Location

tajikistan

nurek town

vaksh river

What is done

Construction and installation works: dismantling, overhaul including replacement of the impeller and installation of the hydraulic unit, dismantling, overhaul and installation of the pre-turbine ball valve

features

Put into operation

1971

Number of hydraulic units

3

Type of turbine

Kaplan

The installed capacity of hydroelectric

40 Mw

Checkout our projects

Baypazinskaya HPP

Hydroelectric power plant on the Vakhsh River

Vartsikhe HPP

Hydroelectric complex in the river Rioni

Delivery of the equipment

SEP Electrotyazhmash

Designing & Engineering

OJSC Power Machines

Industrial construction

Andritz Hydro GmbH

Installation work

PJSC Dnipro-SGEM

Manufacturer

PJSC Turboatom

STM Power a.s.