BAYPAZINSKAYA HPP

Tajikistan

About

Baypazinskaya HPP is a hydroelectric power plant in Tajikistan on the Vakhsh River, with a capacity of 600 MW (four 150 MW units) with an annual output of 2.5 billion kW. h

Baypazinskaya HPP
date

started at march 2011

finished at june 2012

Location

tajikistan

vakhsh river

What is done

A complex of works was carried out, namely dismantling of impeller parts, reconstruction of seals and bypass hydraulic valve and installation of new impeller parts and seals

features

Year of construction

2007-2012

Number of hydraulic units

2

The installed capacity of hydroelectric

380.32 MW

Runner diameter

5.3 m

Rated speed

150 rev./min.

Type of turbine

Vertical radial-axial (Francis)

Calculated pressure

163.35 m

Generator

CB1 1182 / 300-48TV4
rated power - 375 MW

Checkout our projects

Rogunskaya HPP

Hydroelectric power plant under Vakhsh cascade

Nurekskaya HPP

Hydroelectric power plant near the town of Nurek

Delivery of the equipment

SEP Electrotyazhmash

Designing & Engineering

OJSC Power Machines

Industrial construction

Andritz Hydro GmbH

Installation work

PJSC Dnipro-SGEM

Manufacturer

PJSC Turboatom

STM Power a.s.

Copyright 2018. SGEM Group S.R.O. All rights reserved.